42-328. Manufactured Home Park (MHP) Site Plan Review
- Approval Authority. Technical Review Committee (TRC).
- Staff Review. All members of the TRC shall sign off on the proposal for approval. The TRC shall not approve a site plan unless it makes written findings that the regulations of this Chapter that set forth specific development standards have been met. The TRC shall take action within 30 days of reviewing the site plan.
- Approval. The proposal meets all requirements of this Chapter, and other statutes, ordinances and regulations of the County as submitted and is approved. If the site plan is approved by the TRC the applicant may proceed with other requirements necessary to obtain a building permit.
- Conditional Approval. The proposal exhibits only minor deficiencies with regard to this Chapter and other statutes, ordinances and regulations of the County and, after corrections have been made, can be approved. If the site plan is granted conditional approval by the TRC the applicant shall revise and resubmit the site plan to the MHP Administrator. The MHP Administrator shall review the revised site plan and, if it meets the approval conditions and is otherwise substantially unaltered, shall signify on the plan the change from conditional approval to approval. The MHP Administrator has the right to resubmit the revised site plan to the TRC for complete review if deemed necessary. If the site plan is not revised within 60 days to meet the approval conditions, or the applicant notified the MHP Administrator of unwillingness to revise the site plan, it shall be deemed denied.
- Denial. The proposal cannot be approved as it exhibits deficiencies and/or is not in compliance with this Chapter or other statutes, ordinances and regulations of the County which make it completely ineligible for revision and resubmittal. If the TRC denies the site plan, reasons for the denial shall be stated in writing.
- Permit Validity. The MHP Administrator shall grant MHP Construction Permits and MHP Completion of Improvement Permits only after TRC review and approval of the site plan. Minor changes to the location, siting or character of manufactured homes or other structures may be authorized by the MHP Administrator if required by engineering or other circumstances not foreseen at the time the site plan was approved, provided that such changes adhere to the requirements set forth in this Chapter. Where such changes are major (including proposed increases to the number of units or non-accessory structures), the site plan shall be resubmitted and reviewed by the TRC.