42-115. Cost Estimate Standards
Plans, specifications, quantities, unit costs and estimated total costs shall be provided by the applicant to the Subdivision Administrator. Cost estimates shall:
- Be prepared by a professional engineer licensed in N.C., or certified by a professional land surveyor or landscape architect who is routinely engaged in cost estimates and licensed in N. C., at the applicants’ expense. Water and sewer system infrastructure improvements shall be prepared by a professional engineer licensed in N. C. at the applicant’s expense.
- Provide a schedule for initiation and completion of work.
- Include separate estimates for roads, bridges, water and sewer infrastructure, stormwater infrastructure, pedestrian infrastructure, utilities (including electrical power, natural gas and communication lines), etc., consistent with the approved design plans construction specifications.
- Include separate estimates for any off-site infrastructure improvements such as roadways, stormwater system, water system, sanitary sewer system, etc., are required to be included in the improvement guarantee.
- Include all Federal and /or State mitigation fees due but not paid at the time of the execution of the improvement guarantee. Proof of payment for remediation fees shall be provided to the Subdivision Administrator.
- Include all professional engineering and land surveying fees associated with the bidding and award, construction contract administration and engineering certifications associated with the development of the infrastructure for the proposed development.